SRE designed and installed a 3-ton pit-mounted goods lift that lets a Sanand auto-component plant move finished pallets between floors without forklift queues.

Since 2011, SRE Material Handling Equipment has been building lifts, stackers and cranes in Ahmedabad for factories across India. This case study shows how our engineers solved a two-floor transfer problem at a Sanand plant, from the first site visit to the final load test.
Every lift we deliver is fabricated at our own workshop and tested under load before handover. As an ISO 9001:2015 certified manufacturer, we document each step: survey, design, fabrication, installation and testing. Clients can request these records at any time.
The client packed finished components on the ground floor and stored them in a dispatch area on the first floor. The move relied on a worn manual trolley and one shared forklift. During peak shifts, pallets waited 20 to 25 minutes, and workers carried heavy cartons up the staircase, which risked injury. The only space between floors was a narrow shaft, so a standard off-the-shelf lift would not fit.
Our team first visited the site to measure the shaft, pit depth and floor load. We then designed a 3-ton scissor-type goods lift to fit inside that shaft. The heavy MS frame was fabricated at our Ahmedabad workshop. Twin cylinders and a compact hydraulic power pack sit beneath the platform. Each gate carries an interlock sensor, so the lift cannot run while a gate is open. After installation, we tested the lift at 1.25 times its rated load and handed it over only once it passed.
A pallet now travels from the ground floor to the first floor in about 40 seconds, and the forklift is free for yard work. Staircase carrying has stopped completely. In the first three months there were no safety incidents, and the end-of-shift dispatch rush eased noticeably.
"βWe needed a lift that fit our tight shaft and could be trusted every day. SREβs team measured everything on site, explained each safety feature, and handed over on the date they promised. Our dispatch flow is much smoother now.β"
β Vinod Thakker, Plant Head, Sanand